Subcontract change orders (SCOs)
After a change order is approved, you can create an SCO with the potential change order (PCO) items that affect the subcontractor.
The SCO includes a banner that displays:
- Cost - Original contract: The original value of the contract.
- Cost - Changes to date: The total applied cost from the previous SCOs for the contract.
- Cost - This change: The total applied cost from the current SCO.
- Cost - Contract to this CO: The original contract value plus the total applied cost from the previous SCOs and the current SCO.
- Time - Original contract: The original substantial date of the contract.
- Time - Changes to date: The total number of approved days from the previous SCOs for the contract.
- Time - This change: The number of approved days from the current SCO.
- Time - Contract to this CO: The original substantial date plus the total number of approved days from the previous SCOs and the current SCO.
Open the Subcontract change orders module
- In the project menu, select .