Allocations by change order stage

The following tables display which allocations apply by change order stage.

Table 1. Budget allocations
Approximate RevisionsPending RevisionsApproved RevisionsNo Allocation
Owner ChangesYou entered an estimated amount but don't have a quote yet.Table check mark
You have a quote for the proposed amount, and you're waiting for the owner's approval. Table check mark
The owner approved the change, and you're ready to write the subcontract change. Table check mark
Internal ChangesYou want to use extra funds in the Uncommitted Costs column to pay for the change, and you've entered an estimated amount. Table check mark
You want to use extra funds in the Uncommitted Costs column to pay for the change, and you have a quote for the proposed amount from the subcontractor. Table check mark
You want to use extra funds in theUncommitted Costs column to pay for the change, you've approved the cost of the change, and you're ready to write the SCO. Table check mark
You have no funds set aside to cover the cost of the change, and you only have an estimate. Table check mark
You have no funds set aside to cover the cost of the change, and you have a quote from the subcontractor for the proposed amount. Table check mark
You have no funds set aside to cover the cost of the change, you've approved the cost of the change, and you're ready to write the subcontract change. Table check mark
Table 2. Cost allocations
Approximate CommitmentPending CommitmentUncommitted CostUse Uncommitted Cost (Pending)Use Uncommitted Cost (Approximate)Use Uncommitted Cost (Approximate)
Owner ChangesYou entered an estimated amount but don't have a quote yet.Table check mark
You have a quote for the proposed amount, and you're waiting for the owner's approval. Table check mark
The owner approved the change, and you're ready to write the subcontract change. Table check mark
Internal ChangesYou want to use extra funds in the Uncommitted Costs column to pay for the change, and you've entered an estimated amount. Table check mark
You want to use extra funds in the Uncommitted Costs column to pay for the change, and you have a quote for the proposed amount from the subcontractor. Table check mark
You want to use extra funds in theUncommitted Costs column to pay for the change, you've approved the cost of the change, and you're ready to write the SCO. Table check mark
You have no funds set aside to cover the cost of the change, and you only have an estimate.Table check mark
You have no funds set aside to cover the cost of the change, and you have a quote from the subcontractor for the proposed amount. Table check mark
You have no funds set aside to cover the cost of the change, you've approved the cost of the change, and you're ready to write the subcontract change. Table check mark