General

In the settings, you can change the general settings for drawing sets, drawings, specifications, and record types. The settings are saved automatically.

Open the general record settings

  1. Open the record settings.
  2. Select the item type.
  3. On the settings menu, select General.

Financials

See below for a list of general settings that apply to each financial report.

Applications for Payment (AFPs)

Budgets

Change Order Requests (CORs)

Contract Invoices

Contracts

Cost Forecasts

General Invoices

Potential Change Orders (PCOs)

Prime Contract Change Orders (PCCOs)

Purchase Orders (POs)

Subcontract Change Orders (SCOs)

Records

See below for a list of general settings that apply to each record type.

Drawings

Issues

Punch Items

Requests for Information (RFIs)

Specification Sets

Specification

Submittals

Availability

If you make an item type available, anyone with the related permissions can view, create, and edit the items.

Applies to: Drawing sets drawings, specification sets, specifications, all record types except AFPs, CORs, contract invoices, contracts, general invoices, PCOs, PCCOs, POs, and SCOs

Note: To ensure that you can process specification documents in specification sets, turn on the setting for specifications.
Tip:

In submittal records, the Submittal Package field displays the:

  • Submittal package records if submittal packages are available.
  • Lookup items are removed from the field, but they are restored if you make submittal packages unavailable again.

  • Submittal Package lookup list if submittal package records are unavailable.
  • Submittal package record links are removed from the field, but they are restored if you make submittal packages available again.

Make an item type available

  • In the General section, select the Enable ItemType checkbox.

Banner

Applies to: Budgets

You can select which column amounts appear in the banner at the top of the budget.

Customize the budget banner

  • In the Banner section, select an option for each field.

Change order consolidation

Applies to: AFPs

When you add a PCCO to an AFP, the setting for consolidating COs affects how the change orders are added to the Detailed Items grid:

  • If the setting is off, each PCO that's linked to the PCCO is added as a separate line item.
  • If the setting is on, the PCCO is added as a single line item.

Turn the setting on or off

  • Select the Consolidate COs toggle.

Default budget and cost allocations

Applies to: PCOs

When you add new items to potential change orders, the default budget and cost allocations are selected automatically.

Set the default allocations

  1. In the General section, from the Default Bdgt Allocation list, select an allocation.
  2. From the Default Cost Allocation list, select an allocation.

Default budget approval

Applies to: Contract invoices, contracts, general invoices, PCOs, POs, and SCOs

You can set whether the Approved for Budget toggle is on or off when new records are created.

Note: For contract invoices, you can also set the default budget approval for users without the Can Access Contract Invoices for All Companies permission.

Set the default setting for budget approval

  1. In the General section, turn the Default Approved For Budget toggle off or on.
  2. If needed, in the contract invoice record settings, turn the Default Approved For Budget for Users with Limited Access toggle off or on.

Default Contract Rule

Applies to: Contracts

Note: This information applies only to the Enterprise version.

When you create a contract, the default contract rule is selected automatically.

Select the Default Contract Rule

  • In the General section, from the Default Rules Code list, select a rule.

Default drawing group

Applies to: Drawing sets

When you create a drawing set, the default drawing group is selected automatically. The drawing group is part of the unique key that identifies each drawing.

For drawings in the drawing set, the default drawing group or lookup list is used. If a source in the following list is unavailable, the next one is used:

  1. Default drawing group for drawing sets
  2. Default drawing group for drawings
  3. First option in the Drawing Group lookup list

Change the default group for drawings

You can change the default group for drawings in the field attribute settings.

Default group for drawings in the field attributes

Default group for drawings in the field attribute settings

Set the default group for drawing sets

  • In the General section, from the Default Group list, select an option.

Default retainage values

Applies to: Contracts

When you create new contracts, the default retainage values are filled in automatically on the Detail tab.

Set the default retainage values

  1. In the General section, in the Default Stored Material Retainage field, enter the default percentage.
  2. In the Default General Retainage field, enter the default percentage.

Default shipping information

Applies to: Purchase orders

When you create a purchase order, the Ship To field is filled automatically with the job address, telephone number, and fax number from the project form.

Note: The default telephone and fax numbers are added to the Ship To field only when the default address is also used.

Turn on the default ship to setting

  • In the General section, turn on the following toggles:
    • Use Job Address as Default Ship To
    • Use Job Tel/Fax in Default Ship To

Default specification group

Applies to: Specification sets

When you create a specification set, the default specification group is selected automatically. The specification group is part of the unique key that identifies each specification.

Set the default group

  • In the General section, from the Default Group list, select an option.

Field calculations

Applies to: Budgets

You can control how certain budget columns are calculated. These settings affect the budget grid and reports.

Change how the actual cost to complete and actual percent complete columns are calculate

  • In the Field Calculations section, turn the Include Forecast Cost in Actual Cost To Complete and Actual Percent Complete toggle on or off.
    • On: The Actual Cost To Complete and Actual Percent Complete columns are based on the Forecast Cost amount.
    • Off: The Actual Cost To Complete and Actual Percent Complete columns are based on the Projected Costs amount.

Change how the over / under columns are calculated

  • In the Field Calculations section, from the Over/Under Calculation list, select an option:
    • Cost - Budget: The Current Over / Under, Projected Over / Under, and Forecast Over / Under columns are calculated using the cost minus the budget. A positive value represents a loss because the cost is greater than the budget.
    • Budget - Cost: The Current Over / Under, Projected Over / Under, and Forecast Over / Under columns are calculated using the budget minus the cost. A positive value represents a savings because the budget is greater than the cost.
Tip:

In the budget banner, the tooltip indicates how the over / under columns are calculated. After you change this setting, close and then reopen the budget to see the updated tooltip.

Over / under calculation tooltip in the budget

Budget tooltip for the over/under fields

ISO 19650 formats

Applies to: Drawings

  • If selected, ProjectSight enables ISO 19650 fields like suitability and revisions and applies Information management settings to your drawings.
  • If selected, this option links Information Management settings to Drawing settings.
  • If cleared, ProjectSight relies on standard numbered versioning (1, 2, 3).

To turn the setting on or off:

  • Select the Enable ISO 19650 Formats checkbox.

Labor card display

Applies to: Daily reports

You can set how the crew information is displayed in new labor cards:

  • Basic (hours/days): The labor card displays the total hours or days.
  • Basic (workers & hours/days): The labor card displays the number of workers and the total hours or days.
  • Detailed: The labor card displays the number of workers, the budget codes, the total hours or days, and a detailed grid of the company contacts that are assigned to the crew.
  • You can also add workers when you add a labor card to a daily report. However, those workers aren't added to the Contacts tab of the company.

Set the labor card display

  • In the Labor section, from the Document As list, select an option.

Labor summary unit of measurement

Applies to: Daily reports

You can set the unit of measurement for the labor summary in daily reports. When labor details are added for a crew, the quantity is converted for the summary based on the hours per day from the Crews tab of the company record:

  • If the labor is summarized in days, and the labor card uses hours, the logged hours are divided by the hours per day.
  • If the labor is summarized in hours, and the labor card uses days, the logged days are multiplied by the hours per day.

Set the unit of measurement for the labor summary

  • In the Labor section, from the Summarize As list, select an option.

Linking to drawing annotations

If you make a record type available for linking to drawing annotations, for Enterprise, anyone with the related permissions can select it from the list for linking records. For Free, you can select it from the list for linking records.

Applies to: Drawings, all record types except financial records, specification sets, and specifications

Allow linking to annotations

  1. In the General section, ensure that the Enable RecordType checkbox is selected.
  2. Select the Enable Linking to Drawing Annotations checkbox.

Numbering

You can set up autonumbering, so the item number is incremented for each new item.

The generated number is unique for that item type in the current project. The number is the next available one after the last generated number.

Applies to: Drawing sets, all record types except daily reports, general invoices, and meeting minutes

Autonumbering doesn't include letters or formatting.

Turn on autonumbering

  1. In the Numbering section, select the Auto Increment Numbers checkbox.
  2. In the Number of Characters field, enter the minimum number. For example:

    You set the minimum number of characters to 2.

    • The first item number is 01.
    • The next item number after 99 is 100.
Note: The Number of Characters field always applies to child records such as PCO items, but those record numbers are still editable.

Update the Number of Characters

  1. In the Number of Characters field, enter the minimum number, and then press Enter.
  2. In the Update Number of Characters dialog, select Yes.

    For existing non-draft records, zeroes are added to or removed from the beginning of the record number.

Note: For records that were created when autonumbering was off, the record number isn't updated.

Publishing notification

Applies to: Drawing sets, specification sets

When you publish drawings in a drawing set or specifications in a specification set, you can set the default group that will be notified:

  • Project Participants: All the project contacts.
  • Drawing or Specification Participants: The author, assignees, and courtesy copy recipients.
  • For drawing sets, notifications are also sent to users who add a comment on the Comments tab.

Set the default group for publishing notifications

  • In the General section, from the Publish Notification To list, select an option.

Quick upload folder

Applies to: All record types

You can set the quick upload folder path for files that are uploaded and linked to records. The folder path can contain:

  • Subfolders with a backslash (\) between folder names. For example:

    Folder path with subfolder and variable

  • A record variable in the last folder of the path.

    The following variables are available:

    • [[Record_Nomenclature]]: Nomenclature for a single record.
    • [[Record_Nomenclature_Plural]]: Nomenclature for multiple records.
    Record nomenclature

    For example:

    Folder path example

    Folder path with variable

  • If you change the folder path:

    • The quick upload folder is updated in the File Library after the next file upload
    • A new quick upload folder may be created instead of updating the existing folder, but the files are moved to the new folder.
Note: If you rename or move the quick upload folder in the File Library, it reverts to the folder path from the settings after the next file upload.

Edit the quick upload folder

  • In the Quick Upload section, enter the folder path in the Folder Path field.

    A preview of the folder path is displayed below the field.

Review time

When you create a record, the Due Date field is set automatically based on the number of review days after the Created On field. However, you can still edit the dates.

Applies to: Drawing sets, all record types except AFPs, checklists, contracts, daily reports, PCCOs, SCOs, specification sets, and specifications

Note: If the review time is set to 0, the Due Date field is empty when a record is created.

Set the number of review days

  • In the General section, in the ItemType Review Time (days) field, enter the number of days.

Revision number

You can select how revision numbers are set for uploaded drawings.

Applies to: Drawings

The following options are available:

  • Sequential: If the drawing is the first revision in the drawing series, the revision number is automatically set to the drawing revision default from the field attributes. If the drawing is a subsequent revision, the revision number is incremented automatically based on the drawing marked as Current.
Note: You can also manually edit the revision number for a drawing.

Set the revision number

  • In the Revision number section, select an option.

Sharing

You can select which users have access to an item type.

Applies to: Drawing sets, specification sets, specifications, all record types except daily reports

Note:
  • Other factors also affect a user's access to specific records.
  • Regardless of the sharing setting, all PCOs and PCO items are available for linking to CORs, PCCOs, and SCOs. Linked PCOs and items are visible to all users in those records.

Change the sharing setting

  1. In the Sharing section, under Default for New Records, select an option:
    • Share with Entire Project: All project users. In the Sharing panel of new records, the Entire Project option is selected by default.
    • Share with Companies Participating in the Record: Only users from participating companies. In the Sharing panel of new records, the Participating Companies option is selected by default.
  2. In the Update Existing Records dialog, select an option:
    • Yes: The selected option is applied to all existing records, including locked records and draft records from other users, and is the default for new records.
    • No: The selected option is not applied to existing records but is the default for new records.
    • Cancel: No changes are applied, and the sharing setting reverts to the previous selection.
  3. If the Share with Companies Participating in the Record option is selected, select the PrimaryCompany may always access all ItemType checkbox.

    Users from the primary company, defined in the Project form, have access regardless of their involvement or the sharing setting in the record. However, they must have the View permission. For example:

    Users from the project's primary company, Company A, are allowed to access all RFIs. A user from Company B creates a non-draft RFI and limits access to participating companies. Company A users with the View permission for RFIs can view this RFI even though Company A is not a participating company.

Snapping for measurement annotations

If snapping is on while you draw a measurement annotation, the lines are moved automatically to the nearest point or line in the drawing. If you move or resize that annotation, snapping is no longer applied.

See Measuresments.

Applies to: Drawings

For example:

Snapping example

Drawing a measurement annotation when snapping is on

Note:
  • You can temporarily turn off snapping if you press the Shift key while you draw a measurement annotation.
  • Snapping isn't supported in raster drawings.

Turn on snapping for measurement annotations

  • In the General section, select the Enable Snapping for Measurement Annotations check box.

Superseded stamp

If you turn the superseded stamp on, published drawings with the Not Current status are overlaid with the stamp in the drawing viewer.

See Drawing Statuses. The stamp is also included when the drawings are downloaded or included in a report.

Applies to: Drawings

Note:
  • If a drawing is included in an emailed report, then marked as obsolete, and then opened from the report, the drawing is overlaid with the stamp.
  • This feature is only supported in the ProjectSight web app.

You can use the default image or upload a custom image. The supported file types are .bmp, .gif, .jpg, and .png. For example:

Superseded stamp

Default superseded stamp on an old revision

Use the default stamp

  1. In the Superseded Stamp section, select the Show Superseded Stamp check box.
  2. Ensure that the Use Default Image toggle is on.
  3. From the Stamp Position list, select where the stamp will appear on the drawings.

Use a custom stamp

  1. In the Superseded Stamp section, select the Show Superseded Stamp check box.
  2. Select Upload.
  3. Select an image file as follows:
    • Drag the image file from your computer to the Upload Image dialog.
    • Select Browse, and then select the image file.
  4. In the Crop the image dialog, do any of the following:
    • To move the image, select and drag the middle of it.
    • To resize the image, select and drag a sizing handle.

      Image sizing handle example

  5. Select Crop icon(Crop).
  6. The Use Default Image toggle is turned off automatically.
    Tip: If you switch back to the default image, the custom image remains in the system so that you can use it again.
  7. From the Stamp Position list, select where the stamp will appear on the drawings.

Telephone and fax in company Address

Applies to: Transmittals

If this setting is turned on, the telephone and fax numbers are included in the company address when you create a transmittal.

Note: Changes to this setting only affect new records.

Change the telephone and fax number setting

  • In the General section, turn the Include Tel/Fax in Company Addresses toggle on or off.

Units and hours

Applies to: Budgets

The units and hours setting affects the visibility of the related fields and columns in the following records:

  • Budget items
  • Contract invoices
  • PCOs
  • Purchase orders

For example:

When the units and hours setting is on, the related columns are available in the budget.

Columns related to units and hours

Note:
  • If you unlock the budget settings at the project level and then add budget items in the project, the settings can't be locked again.
  • You can't turn off the units and hours setting after budget items are added in a project.

Allow units and hours in the budget

  • In the General section, turn on the Enable Units and Hours toggle.

    Units and hours toggle

Weather units of measurement

Applies to: Daily reports

You can select the unit of measurement for weather details in daily reports. Changes to the default values are only applied to new weather cards.

Set the unit of measurement

  • In the Weather section, from the UOM list, select an option.