Manage PCO items
You can manage PCO items.
A budget and cost allocation must be selected for each PCO item. As the PCO moves through the change order process, you can update the allocations and the proposed and approved amounts for each item. The amounts are applied to the budget if the PCO is approved.
- Only committing contracts can be selected in the Contract Number column of the Potential Change Order Items grid.
- A PCO item can be linked to one SCO at a time. Then the (Cost impacts) Applied Amount and (Cost impacts) Allocation cells are locked, and the Locked checkbox is selected in the grid.
- When a PCO item is part of an approved SCO, the cost allocation is set automatically to Approved Commitment.
- If a PCO is linked to a BCM record such as a change order, the PCO is visible in the record to all users regardless of the company that's associated with the PCO items.
- The Applied column is updated if its value is 0 and then a value is entered in the Proposed column or if a value, including 0, is entered in the Approved column.
- The (Budget) Applied Amount, Include in
COR/PCCO, Markup percent, Markup Amount and Revenue Amount columns are
locked if:
- The PCO is associated with a PCCO, and there are locked AFPs in the period associated with the PCCO’s date.
- The PCO is associated with a PCCO, and that PCCO has been locked by a subsequent PCCO.
Each PCO item row contains icons that indicate if there are assignments and comments or attached files that are quick uploads or selected from the file management system.
If you don't have permission for the attached files, the comments icon is still blue, but the attached files aren't available when you open the PCO item.
View PCO items
You can create PCO items.
Add a PCO item
Track the items in a potential change order after creating the PCO.
You can update the PCO item later with the proposed and approved amounts.
Add revenue to a PCO item
You can add revenue information to a PCO item.
Add a unit price for a PCO item
You can add a unit price for a PCO item.
Update the amounts for a PCO item
You can update the amounts for a PCO item.
Cancel a PCO item
You can cancel a PCO item.
Remove a PCO item
You can remove a PCO item.
- If the PCO item is locked, remove the item from the SCO.
- Open the PCO.
- Select the checkbox for the PCO item.
- Select Remove.